Dunkerque LNG to boost its reloading capacity

September 1, 2017

Share this:

Dunkerque LNG announced today that it will adapt its terminal to expand its reload capacity from up to 4,000cbm/h to up to 9,000cbm/h.

The new facility is expected to start operating in the fourth quarter of 2018. For the commissioning of this new facility, Dunkerque LNG anticipates the stop of send out and the unavailability of the jetty during all of September 2018.

The contract has been awarded to TS LNG, a joint venture between Techint E&C and Sener. The works include replacing eight pumps and adding an additional BOG compressor.

Edited from Dunkerque LNG note and Techint press release.