Bulgargaz to book additional 0.5 bcma at Alexandroupolis LNG

August 31, 2022

Share this:

Bulgargaz will apply to book additional storage capacity of 0.5 bcma at the 5.5 bcma floating receiving terminal in Alexandroupolis for 10 years starting from the date of commissioning. The terminal is being built and will be operated by Gastrade. The start-up is expected by the end of 2023. The terminal will be linked to the Greece-Bulgaria gas interconnector which is scheduled for commissioning on October 1.