Cameron LNG starts commissioning third liquefaction train
April 22, 2020
Sempra Energy has started the commissioning of the third liquefaction train of Cameron LNG. Following FERCs approval on 21 April to start introducing of pipeline feed gas to the third unit, Cameron LNG has started ramping up the feed gas deliveries to the third train. The third liquefaction train is included within Phase 1 of the Cameron LNG export project, which includes three liquefaction trains that will enable the export of approximately 12 million tonnes. The project is foreseen to start operations in Q3 of 2020.
Edited from Sempra Energy’s press release