Hammerfest LNG to restart operations in May 2022

January 31, 2022

Share this:

The start-up date of the Hammerfest LNG plant after the fire in September 2020, was pushed from 31 March 2022 to 17 May 2022 due to consequences from Covid-19 and related operational restrictions. According to Equinor, the progress is impacted by lack of staff due to quarantine and isolation measures, combined with restrictions and narrow working areas.

Edited from Equinor press release