LNG Croatia departs from yard

September 15, 2020

Share this:

Huarun Dadong and CSSC Hudong-Zhonghua have completed the reconversion of the “Golar Viking” vessel into the renamed “LNG Croatia” which has been delivered to the state-owned Krk terminal developer LNG Croatia and Golar. The vessel is expected to arrive in Croatia on October 20, 2020. Croatia is set to launch the Krk facility on January 1, 2021. It will have a send-out capacity of up to 2.6 bcm/y. The costs of the LNG import project amount to 233.6 M€ ($276.8 million) with EU providing 101.4 M€ from the Connecting Europe Facility.

Edited from Croatia LNG’s press release