Montoir-de-Bretagne LNG terminal to resume send-out

May 28, 2021

Share this:

French LNG terminal operator Elengy halted send-out at Montoir-de-Bretagne terminal on 4 May after detecting leak on the insulating joint in the gas pipeline linking the terminal to the French transmission grid. The repair works started on May 12 and were completed on May 28. Elengy’s teams are starting the works to progressively resume the gas send-out into the transmission grid.

Edited from Elengy press release